By Joseph Kiggundu
Wakiso District Head of Procurement William Mayanja has attributed delays in the implementation of road construction projects to difficulties in securing access to land, adverse weather conditions and international conflicts that have disrupted the transportation of construction materials.
Mayanja said the challenges were not necessarily a result of contractors’ inefficiency but were sometimes beyond their control, particularly where residents take time to agree to provide access to land without compensation.
“Of course, the causes of delays in our road construction projects are many. They are not necessarily because our contractors are ineffective, but there are difficulties in securing the right of way because some people take long to agree since there is no compensation. Then there are weather conditions and international wars, which make it difficult to transport road construction materials such as bitumen,” Mayanja said.
He made the remarks during a bid-opening exercise for the construction of three additional roads and two drainage systems in Wakiso District and Nansana Municipality.
The exercise was held recently at Rockstone Gardens near Wakiso District headquarters.
According to Mayanja, the roads earmarked for construction include Jolijo Road and Magere-Luteete Road in Wakiso District, as well as Kiti-Buwambo-Kigoogwa Road in Nansana Municipality.
The planned drainage projects include Jalaja Drainage System in Wakiso District and Kasolokamponye Drainage System in Nansana Municipality.
Mayanja also dismissed claims that road construction contracts in the district are predominantly awarded to foreign companies, particularly Chinese contractors.
He said several competent Ugandan construction firms continue to secure government contracts, citing Abubaker Construction Company, Maltplex and Sider among the local companies involved in construction works.
He explained that the district undertakes comprehensive evaluations and due diligence before awarding contracts to ensure that successful bidders have the necessary technical and financial capacity to execute the projects.

The evaluation process, he said, includes examining contractors’ previous work, verifying their experience and assessing their financial capacity and cash flows to establish whether they can complete projects within the required timelines.
Mayanja added that the district also conducts technical assessments and verifies the credentials of international construction companies seeking to undertake projects.
He further noted that tax compliance is among the requirements considered during the procurement process, with companies expected to present income tax clearance documentation from the Uganda Revenue Authority (URA).
According to Mayanja, the procurement advertisement was published in September and closed on November 13, 2026.
He said the next stage would involve environmental and social safeguards assessments before the projects proceed to the subsequent implementation stages.